Starting December 31, 2026, Florida's 9th Edition changes how adhesive-set roof tile is tested and what the test report has to show in the High Velocity Hurricane Zone, which covers Miami-Dade and Broward. The state's analysis also says field checks use numbered roof zones. RAS 118, RAS 119 and RAS 120 require tile fasteners to reach ¾ inch into the roof sheathing, the panels that form your roof deck, even when tile support strips are used. The analysis explains what changed. Your roofer can check the full standard and product approvals to see what applies to your home. At Apex Roofing Solutions Corp., we offer a free roof inspection and put every price and fee in writing. After the signing deposit, payments are tied to permit approval and passed city inspections. Call 305-290-2482 to book your inspection.
Key takeaways
- Miami-Dade's Permitting and Inspection Center says the 9th Edition takes effect December 31, 2026.
- TAS 101 Section 7.6.3 allows the tile manufacturer to specify an alternative amount of adhesive when it follows the applicable standards and product approvals.
- TAS 101 Section 11.1.1 adds the average amount of adhesive or mortar to the test report. It also adds the average contact area on the tile and underlayment.
- TAS 106 Section 6 uses Zone 1, Zone 2 and Zone 3 for checks done on the roof.
- Under RAS 118 and RAS 119, the tile fastener has to go ¾ inch into the sheathing even when battens are used.
Who can say how much adhesive to use in the tile test?
Under TAS 101 Section 7.6.3, the tile manufacturer can call for a different amount of adhesive than the adhesive manufacturer specifies. The alternative can be used if it follows the applicable standards and product approvals. The Florida Building Code's analysis identifies this as a change to how mortar or adhesive-set tile systems are tested.
TAS 101 measures how well the tile system being tested holds up when you pull upward on it. If your roofer proposes an adhesive-set system, ask whose adhesive amount is in the proposal and which approval supports it. If two roofers quote the same tile but plan to attach it differently, you have something specific to check.
What does the test report have to show about how the tile bonds?
Under TAS 101 Section 11.1.1, the report must add the average amount of adhesive used, measured in grams, or the average amount of mortar used. It also has to show the average contact area on both the tile and the underlayment, the layer under the tile. The report must include measurements or diagrams that show how far the adhesive spreads on each surface.
Think about what happens when you press the tile into the adhesive. The weight tells you how much material was used. The contact area tells you how much of each surface the material actually touched. The lab test report for the system must now show both details.
Why do field test records now say Zone 1, Zone 2 and Zone 3?
The state's analysis says TAS 106 Section 6 now calls these areas Zone 1, Zone 2 and Zone 3 to match ASCE 7, the standard referenced for wind loads. The old names were field, perimeter and corner. This section covers how many tiles are tested on the roof.
TAS 106 covers checks done on the roof for mortar-set and adhesive-set tile systems. It also covers roofing made of separate rigid pieces that are mechanically attached. If your roofer names a zone in a field test record, ask them to point it out on your roof plan. Then you can see where the tiles in the record were checked.
How far does a tile fastener have to go in when there is a batten?
Even when the tiles sit on battens, the strips that support them, tile fasteners have to reach ¾ inch into the roof sheathing. That's what the Florida Building Code's analysis says RAS 118 and RAS 119 Section 2.01A require. The same analysis records that fastener change in RAS 120, the standard for mortar and adhesive-set tile application.
The ¾ inch is the part of the fastener that goes into the sheathing itself. If the proposal includes battens, ask your roofer to show you the fastener and how it gets through the layers above the sheathing. The state's analysis also clarifies that RAS 118 and RAS 119 apply to slopes of 4:12 or greater. On a 4:12 roof, the roof rises four inches for every 12 inches you measure horizontally.
Where can my roofer show me that the underlayment can resist wind?
Ask your roofer for the current underlayment approval. Have them show you the page that says it is approved for use under tile and gives its resistance to upward wind pressure. The state's analysis says TAS 103, the test for self-adhered underlayments used under tile, no longer covers wind uplift. RAS 127 explicitly requires the underlayment beneath tile to meet the design wind uplift pressures for your roof.
Miami-Dade Product Control says the underlayment needs product approval for use under tile and must show uplift resistance under ASCE 7 or as specified in RAS 127. A Notice of Acceptance, or NOA, is a Miami-Dade product approval document. Ask your roofer to show you the values in the approval and explain how they match the pressures for your house.
Miami-Dade's permitting notice gives December 31, 2026 as the date the code takes effect. It says online applications submitted after 4 PM on December 30 must meet the new edition. If your project is in Broward, ask the building department handling your permit which edition it will use to review your application.
What does Apex put in writing for my tile replacement?
For a tile replacement, we write down the roof system we're proposing and the exact underlayment. We also put the permit fee and payment schedule in writing. If you're worried the bill could go up once the old roof comes off, look at the unit prices in the contract. We price wood deck replacement by the sheet. We price fascia and soffit by the foot. You pay for what we actually replace.
For a home replacement, you pay a $500 deposit when you sign. Of the remaining balance, 35% is due when the city approves the permit. Another 35% is due once the inspection during the job passes. The last 30% is due after the final city inspection passes. If you want to see financing, we put the monthly payment on the quote.
If you're deciding whether to repair your tile roof or replace it, call 305-290-2482 to book a free inspection. We get on your roof and show you photos of it so you can see what needs fixing and what's cosmetic.
Questions homeowners ask
Does the tile manufacturer always get to choose how much adhesive to use?
TAS 101 Section 7.6.3 allows the tile manufacturer to specify a different amount from what the adhesive manufacturer calls for, as long as that amount follows the applicable standards and product approvals. Ask your roofer to show you where that amount is written down.
Do the new roof zone names mean more tiles have to be pulled during a field test?
The state's analysis describes the change to TAS 106 Section 6 as an update to the zone names so they match ASCE 7. Check the full protocol for how many tiles to test and where on the roof to test them.
Does the new edition cancel existing underlayment approvals?
Miami-Dade Product Control says existing Notices of Acceptance remain valid. Its notice says that for permit applications submitted on or after January 1, 2027, underlayment beneath tile may only be installed within the approved uses and applicable uplift resistance listed in the current product approval or Notice of Acceptance.
How much will Apex charge for my tile replacement, and when do I pay?
As of November 11, 2026, our going rate for concrete tile is $9.75 to $11 per square foot installed. Use this range for budgeting. Your price depends on the underlayment, the roof you have now, the system you choose and the complexity of your roof. After the free inspection, we put your price in writing. For a home replacement, you pay $500 when you sign. Of the remaining balance, you pay 35% when the permit is approved. You pay another 35% after the inspection during the job passes. The last 30% is due after the final inspection passes. If you finance the roof, we show the monthly payment on the quote.
Sources
- Florida Building Code 9th Edition analysis of changes to HVHZ test protocols
- Miami-Dade Permitting and Inspection Center notice on the 9th Edition effective date
- Miami-Dade Product Control notice on 9th Edition roofing underlayment updates
- Florida Building Commission overview identifying Miami-Dade and Broward as the High Velocity Hurricane Zone