Do I need a Notice of Commencement to replace my roof in Florida?

Updated November 22, 2026 Reviewed by Brandon Vega, owner, Apex Roofing Solutions Corp. (license CCC1336242)
Old wood plank roof deck with a broken board exposed during a tear-off
Photo: Apex Roofing Solutions

Yes. If the contract you sign directly with your roofer is over $5,000, Florida Statutes section 713.135 requires the permit applicant to file proof of the Notice of Commencement with the building department before the first inspection. Section 713.13 gives the owner or an authorized agent a separate job. When the recording requirement applies, they have to record the notice and post it before work begins. If your contract is $5,000 or less, ask the building department about your job before you assume the inspection threshold answers the recording question. At Apex Roofing Solutions Corp., we offer a free roof inspection in Miami-Dade and Broward. We put every fee in writing. After the deposit, we tie residential payments to permit approval and passed city inspections.

Key takeaways

  • If the contract you sign directly with your roofer is over $5,000, section 713.135 requires the permit applicant to file proof of the notice with the building department before the first inspection.
  • Under section 713.13, the owner signs the notice. The owner or an authorized agent can arrange to record it. When the requirement applies, the notice has to be recorded and posted before work starts.
  • Miami-Dade County calls for a separate notice for each individual permit.
  • If the work described in the notice hasn't started within 90 days after recording, the notice becomes void.
  • At Apex, we put the permit fees in the contract. For a residential job, you pay $500 at signing. Of the balance, 35% is due at permit approval. Another 35% is due after the in-progress inspection passes. The last 30% is due after the final inspection passes.

What roof contract price triggers the inspection paperwork?

Use the full price on the contract you sign with your roofer. That's your direct contract. When it's more than $5,000, Florida Statutes section 713.135(1)(e) requires the permit applicant to file proof of the notice with the building department before the first inspection.

Let's say you sign a $15,000 roof contract and put down $500. The number you use to check the threshold is $15,000. The first payment is just part of the price. The same section applies to cities and counties with building permit systems. So in Miami-Dade or Broward, use that test whether your permit comes from the city or the county.

Miami-Dade County's building department says the notice is required for improvements greater than $5,000. If your price is right at that number or below it, give the department issuing your permit the written scope and the full contract amount. Ask whether you have to record a notice for the work itself. Section 713.13 covers recording and refers to statutory exemptions. The $5,000 test in section 713.135(1)(e) covers what the permit applicant files for inspections.

What does recording the notice mean for my property?

Recording the Notice of Commencement puts your roof project in the county's official records. It identifies your property and the contractor doing the work. Section 713.13(3) says that recording tells the public that construction liens may be recorded. Recording the notice itself creates no lien.

A construction lien is a claim for payment against your property. Miami-Dade County explains why you should pay attention to that. If someone supplies labor or materials for your roof and goes unpaid, that person may have a claim against the property even if you've already paid your roofer. Keep the notice with your contract so you have the project details handy if a supplier or subcontractor contacts you about the job.

Miami-Dade County explains that you may get a document called a Notice to Owner from a subcontractor or supplier. It tells you who's providing work or materials for your project. Keep it with your roof records. Ask your contractor what the sender provided. The county advises getting a release of lien and an affidavit from the contractor for the payment you're making. When you make the final payment, the county advises getting the final release and affidavit showing the subcontractors and suppliers have been paid.

What should I look at before I sign the form?

Start with the property and the contractor. Section 713.13 requires the legal description. It also requires the street address and tax folio number when available. The folio number identifies your property in the county's tax records. The form asks for a general description of the work. It also asks for the names and addresses of the owner and contractor.

Set the form next to your signed roof contract and your permit application. Check that the contractor's name is the business you hired and that the address is for the house getting the roof. Take the legal description from your property records. The statutory form also has a spot for the permit number so you can match it to the right job. Section 713.135 tells the building department to check key details against the permit application. Those include the owner's name and address, the contractor's name, and the job location.

Under section 713.13, the owner signs the notice. The owner or an authorized agent can arrange to record it. In Miami-Dade, the Clerk of the Court and Comptroller lists the original document among its requirements. It also lists the notarized owner signature and the preparer's name and address. If you have a construction lender, the statutory form asks for the lender's information. If there's a payment bond, section 713.13 requires a copy to be attached when the notice is recorded.

Where do I record and post the notice before work starts?

If your work is subject to section 713.13, record the notice at the clerk's office and post it at the house before work starts. The statute lets you post a certified copy of the recorded notice at the job site. You can also post a notarized statement that the notice has been filed for recording, along with a copy of the notice.

In Miami-Dade, the Clerk offers recording in person and by mail. There are electronic options too. The Clerk's own electronic recording service accepts Notices of Commencement. If you submit electronically, check that the notice has actually been recorded before you rely on the submission. Ask for the instrument number. That's the number the clerk assigns to the recorded document. Miami-Dade County says you can also search its official records by owner name and look for document type NCO.

If your permit is in Broward, ask the office that issues it where to send the recording proof and how to check that it made it into your permit file. Section 713.135 allows the applicant to file a certified recorded copy. The applicant can also file a notarized filing statement with a copy or use the clerk's official identifying information. That information can be the instrument number or the official records book and page. Keep your recording details with your permit number so either one is easy to find when an inspection is scheduled.

If a lender is providing construction funds, ask who will make sure the notice got recorded and when they'll check. Section 713.13(7) requires the lender to record the notice before paying construction funds to the contractor. The owner still handles posting at the job site. In Miami-Dade, also check how many permits cover your work. The county directs owners to file a separate notice for each individual permit.

Can I get my permit before the notice is recorded?

Yes. Section 713.135(1)(e) and (f) allow the building department to issue the permit before the notice is recorded. The department can't require recording before you apply. It can't make recording a condition of processing or issuing the permit either. When section 713.13 applies, make sure the notice is recorded and posted before work starts, even if your permit is already approved.

For a direct contract over $5,000, check that the permit applicant filed acceptable proof with the department that issued the permit before the first inspection. Check this even if the notice already shows up in the clerk's records. Ask your roofer which permit number they filed the proof under. If the required proof is missing, section 713.135(1)(e) says subsequent inspections may neither be performed nor approved until the applicant files it.

Keep track of when your crew expects to start and when the first inspection is scheduled. Before the crew shows up, check that the posted document matches the work on the permit. Before the inspection, confirm that the applicant sent the proof to the office that issued the permit. If you have a roof proposal and want to go over the work it lists, you can book a free roof inspection with Apex.

What happens to my notice if the roof job starts late?

Start counting on the date the clerk recorded your notice. Under section 713.13(2), the notice becomes void if the work it describes hasn't actually started within 90 days after recording. If that happens, Miami-Dade County directs you to record a new notice. Check that new recording before work begins.

The 90 days are how long you have to start work after recording. Once you're paying for the work, pay attention to the expiration date. Under section 713.13, the notice generally lasts one year from recording unless a different period applies. The statute treats payments made after the notice expires as improper payments. The statutory form warns that you could end up paying twice for improvements.

If the job runs long or something on the notice is wrong, section 713.13(5) explains how to record an amendment while the notice is still in effect. You can use the amendment to extend the notice or correct an error. You can also use it to add missing information. If you change contractors, that section requires a new notice of commencement or a notice of recommencement. If a contractor changes halfway through the job or you find out the notice expired while you still owe money, take the notices, contract, and payment records to a Florida construction attorney before you pay the balance.

What does Apex put in my roof contract while I handle the notice?

At Apex Roofing Solutions Corp., we pull the permit for your residential roof replacement and handle both city inspections. Before we start, you get the roof price and every fee in writing. The contract shows the permit fees. It also shows the rate for replacing rotten roof decking, which is the wood under your roof covering.

If you're worried the bill will go up after the old roof comes off, look at the unit prices before you sign. We price decking by the sheet. The contract lists fascia, the trim at the roof edge, by its applicable unit. It does the same for soffit, which is the underside of the overhang. You pay for what gets replaced. If you're comparing proposals, ask each roofer to show you the written rate for the same wood work so you can see how they'll charge for it.

You pay a $500 residential deposit at signing. Of the remaining balance, 35% is due when the city approves the permit. Another 35% is due after the in-progress inspection passes. The last 30% is due after the final inspection passes. If you want financing, we'll show you the monthly payment on your quote. When you go through the contract, ask who's coordinating the notice paperwork and which permit number goes with it.

We're based in Miami Lakes and serve Miami-Dade and Broward. Our Florida roofing license is CCC1336242. To book a free roof inspection, call 305-290-2482. We'll get on the roof and show you photos of your own roof. We'll explain what needs fixing before you decide how to proceed.

Questions homeowners ask

Does a roof contract for exactly $5,000 meet the inspection filing threshold?

A direct contract for exactly $5,000 falls outside that paragraph. Section 713.135(1)(e) sets the threshold at greater than $5,000. Ask your building department about your job before you decide whether the separate recording requirement under section 713.13 applies.

Can my roofer sign the Notice of Commencement for me?

Section 713.13(1)(g) requires the owner to sign. The owner or an authorized agent can take care of recording under section 713.13(1)(a). In Miami-Dade, the Clerk lists a notarized owner signature among its recording requirements. The Clerk also lists the name and address of the person who prepared the document.

Can I give the building department the recording number?

Yes. Section 713.135(1)(e) allows you to use the clerk's official recording information, including the instrument number or the official records book and page. Posting the notice at the job site under section 713.13 is a separate step.

Should I use the Notice of Commencement from an older project?

First, check the work description and the permit number. Section 713.13 calls for a description of the improvement. Miami-Dade County directs owners to file a separate notice for each individual permit. If the notice describes different work or goes with a different permit, ask your building department which notice belongs with your roof job.

How will Apex charge me for a residential roof replacement?

We price the job after the free inspection. The contract lists the permit fees and any wood replacement rates. You pay $500 at signing. Of the remaining balance, you pay 35% at permit approval, 35% after the in-progress inspection passes, and 30% after the final inspection passes. If you choose financing, your quote shows the monthly payment.

Sources

Free Estimate

Tell Us About Your Roof

Share a few details and our team will follow up with the next step.

  • Roof repairs, replacements, and inspections
  • Tile, shingle, metal, and commercial roofing
  • Serving Miami-Dade, Broward, Palm Beach and Monroe counties

Prefer to talk to a person?

Call now if you need help today.

305-290-2482