Starting January 1, 2027, Miami-Dade County Product Control says asphalt shingle roof permit applications in Miami-Dade have to show how the shingles over the peaks and sloping outside corners meet the new Florida Building Code requirement for the High Velocity Hurricane Zone (HVHZ). You can use a Notice of Acceptance (NOA), which is a product approval document, showing the new wind testing and classification, or use the attachment method in Florida Building Code section 1518.7.4.2. The county notice leaves it open how your building department will handle an application filed before January 1. At Apex Roofing Solutions Corp., we offer a free roof inspection and put your price and every fee in writing. After the deposit you pay at signing, your payments follow permit approval and city inspections.
Key takeaways
- Miami-Dade County Product Control says the Florida Building Code’s HVHZ requirement applies to Miami-Dade asphalt shingle permit applications filed starting January 1, 2027.
- Section 1518.7.4.1 calls for a modified UL 2375 test at 110 mph. The packaging has to show compliance with a label.
- Section 1518.7.4.2 gives your roofer another way to attach the cap shingles. For each cap shingle, the roofer puts two spots of adhesive on each side of the hip or ridge and follows the manufacturer’s fastening instructions.
- Miami-Dade County Product Control says existing NOAs stay on file. Ask your roofer to name the cap shingle in your proposal and show how it will meet the rule.
Which shingles does the January rule cover?
The July 31, 2026 notice from Miami-Dade County Product Control covers the shingles that cap the peaks and sloping outside corners of an asphalt shingle roof. The requirements come from Chapter 15 of the Florida Building Code for the High Velocity Hurricane Zone, which includes Miami-Dade and Broward counties. A ridge is the peak where two roof surfaces meet. A hip is an outside corner that slopes down from the peak. The rule applies to the pieces that cover those joints.
If you’re looking at a proposal, ask your roofer to show you the hips and ridges on a photo of your roof. Then ask which cap shingle is included in the price. The name of the shingle on the main slopes tells you only part of what you’re buying.
If I sign in December, which rule applies to my permit?
The date to look at is when your roofer files the permit application. That’s the date the county notice uses. The ninth edition of the Florida Building Code takes effect December 31, 2026. The notice calls for compliance on asphalt shingle permit applications starting January 1, 2027. So if you sign in December and your roofer files in January, your application falls within the dates in the notice.
When we replace a roof on a home, the permit stage with the city takes about two to four weeks after signing. If your project is close to the cutoff, ask your roofer when they expect to file. Once they file, ask for the confirmation so you have the actual filing date. If you already filed before January 1, ask your building department how it will handle your application.
What can my roofer show to meet the cap shingle rule?
Miami-Dade County Product Control gives your roofer two ways to meet the Florida Building Code’s HVHZ requirement for cap shingles. One is to show an NOA with the new testing and classification for the cap shingles. The other is to use the attachment method in section 1518.7.4.2. The county says existing NOAs will stay on file, so ask which of the two methods your roofer is using on your roof.
Under section 1518.7.4.1, hip and ridge shingles go through UL 2375 testing and classification at a modified test speed of 110 mph. The packaging has to carry a label showing that the shingles comply with the modified test. If your roofer is using that option, ask to see the NOA with the new testing and classification for the cap shingle on your proposal.
Under section 1518.7.4.2, your roofer puts two spots of adhesive on each side of the hip or ridge before setting each cap shingle. Each spot has to be at least 1 inch across. The roofer puts the spots near the leading edge, fully beneath the part of the cap that stays exposed. The section allows roof cement that meets ASTM D3019 or ASTM D4586, or another adhesive the cap shingle manufacturer specifies. Your roofer also has to follow the manufacturer’s fastening instructions.
How should I compare two bids that say they meet code?
Set the bids side by side. Ask each roofer to put the cap shingle name in writing and spell out how they’ll meet the rule. Then check which roof system each bid includes. Check the underlayment, which is the layer beneath the shingles. Check the product approval too. Those details give you something specific to compare before you decide whether both prices cover the same work.
Ask your roofer directly. Which cap shingle is in this price? What will you show the building department for it? If they’re using the attachment method, ask them to put that method in the scope. If the quote uses the testing option, ask for the NOA that shows the new test and classification. You can book a free roof inspection with Apex Roofing Solutions Corp. if you’d like us to go through those details with you.
What does Apex put in writing for my shingle replacement?
Before we start work, we put the scope and price in your contract. The contract also spells out the permit fees and payment terms. We name the roof system and the underlayment. If we find rotten roof deck wood after the old roof comes off, you have the price per sheet in your contract. You pay for the sheets we actually replace.
For a home roof replacement, you pay a $500 deposit at signing. When the city approves the permit, you pay 35% of the remaining balance. You pay 35% of that balance after the in-progress inspection passes. You pay the final 30% after the final inspection passes. If you want financing, we show the monthly payment on your quote.
We get on your roof and show you photos so you can see what needs fixing and what’s cosmetic. You can call 305-290-2482 to book a free inspection and get a written price if your roof needs work.
Questions homeowners ask
Does the rule apply if my permit application is filed on January 1, 2027?
Yes. Miami-Dade County Product Control says the requirement applies to asphalt shingle permit applications starting January 1, 2027. That includes January 1 itself.
Does my roofer need a newly tested cap shingle for every job?
Miami-Dade County Product Control gives your roofer two ways to meet the rule. Your roofer can show an NOA with the new testing and classification or use the attachment method in Florida Building Code section 1518.7.4.2.
Does the 110 mph number tell me what my whole roof can withstand?
The 110 mph figure in section 1518.7.4.1 is the speed used in the modified UL 2375 wind test. That test is for the shingles that cover the hips and ridges.
What do I pay Apex when the city approves my permit?
For a home roof replacement, you pay 35% of the remaining balance when the city approves your permit. You pay $500 at signing. Another 35% of that balance is due after the in-progress inspection passes. The final 30% is due after the final inspection passes.